The Comores - The Sima Peninsula

Drilling and water collection - Treatment and purification

Date: 2012-2014 

Funding: AFD 

Drinking water conveyance for the Sima peninsula on the island of Anjouan:

 Construction of a conveyance and discharge network: 22 km in cast iron and HDPE (NPS 80 – 200) 

Construction of an HDPE distribution network: supply and laying of 20 km of pipes (NPS 50 – 100) 

Construction of new structures: 

  • 6 reservoirs (50 m3 – 300 m3) 
  • 1 pumping station (40 m3/h) with a TDH of 150 m 
  • 1 water catchment 
  • 2 treatment plants: 1,100 m3/d with physico-chemical treatment 
  • and 365 m3/d with a sand filter 
  • 1 x 10 m3 head pond 

Construction of 530 private connections and 30 standpipes 

Rehabilitation of existing structures (4 water catchments – 3 reservoirs)

 